BMX Pump Track at Clyde Bland Park

City of Tracy Clyde Bland Park

Project Background

A BMX Pump Track (Pump Track) has been identified as a community need in the City of Tracy’s park system, including being identified in the Citywide Parks, Recreation, and Trails Master Plan (Master Plan) as a recommendation to diversify recreational offerings in the community. A pump track is a progressive circular course structure designed for riders to propel themselves forward using an up and down ‘pumping’ motion, instead of pedaling. The Master Plan includes a goal of constructing three (3) pump tracks by 2040 to meet the growing need of the community.

As part of the Fiscal Year 2022/2023 City budget process, the City Council approved the creation of the Clyde Bland Park BMX Pump Track, CIP 78190, and allocated $1 million in funding for the project.

In February 2023, the City hosted two (2) public outreach meetings soliciting feedback on the project including the proposed idea of constructing a Pump Track as an added amenity at the existing Clyde Bland Park.

At the March 2, 2023, Parks & Community Services Commission meeting, staff presented the recommendation to construct an asphalt Pump Track at Clyde Bland Park. The Commission made a formal recommendation to the City Council to codify the location.

Project Status

We are pleased to announce that our project is actively under construction! The utility work was successfully completed. Currently, site finishes have been installed, and we are set to begin enhancements on the existing restroom and basketball court shortly.

We’re thrilled to share that a new entry-level pump track loop will be added to this exciting development once the project team finalizes the updated drawings. Thank you for your continued support from the community.

We eagerly anticipate the opening of this completed section and look forward to sharing more exciting news about the new entry-level track soon!

Project Timeline

  • Conceptual Design Approval: November 7, 2024
  • Construction Documentation: Fall 2024 - Spring 2025
  • Advertise for Public Bidding: Late Spring 2025
  • Award Construction Contract: Summer 2025
  • Construction Start: Late Summer/Fall 2025
  • Partial Opening: Spring 2026
  • Full Opening: Summer 2026