The City of Tracy is building a new Aquatic Center for recreational and competitive use. The long-awaited Aquatic Center will be a community facility owned, operated, and programmed by the City of Tracy, offering recreational/competitive areas, swim lessons and more. The City Council ranked amenities in descending order of priority, as funding permits: 1) a 50-meter competition pool; 2) a recreation and warmup pool; 3) a lazy river; 4) water slides; 5) a toddler area; 6) an indoor pool (optional); and 7) a fitness center (optional).
The proposed timeline for the Aquatic Center is as follows. All dates are subject to change based on weather, equipment and material availability or other potential delays.
The Aquatic Center will be built on the northwest corner of Summit Drive and Corral Hollow Road, located in South Tracy.
The goal is to open the Aquatic Center in Fall 2028 (subject to change).
The current project budget is established at $65 million. Most of that budget, $55 million, is funded by Measure V sales tax revenue and a small amount of developer impact fees. An additional $10 million in funding has been committed by a local developer.
The Aquatic Center will be owned and operated by the City of Tracy.
This page and the social media channels linked below are the sole official channels for information on the City of Tracy Aquatic Center project.
Thank you for your input, Tracy!
Over the past six months, the City of Tracy launched a series of community engagement opportunities to gather your input on the design and programming of the new aquatic center. We heard you loud and clear, and are factoring your valuable feedback into development of the center. There’s still more work to be done; below is a list of what we’ve done so far as well as other opportunities to get involved in the process:
January 2025
Community Engagement Workshops
Stakeholder Meetings
City Council Briefings
Refinement of Conceptual Design
February 2025
Parks and Recreation Commission Workshop
Project Tours by City Staff and Project Team
March 2025
Prepared Final Conceptual Design and Budget
April 2025
City Council direction on programming, design, and budget on April 15th
Allocated $65,000,000 for total project budget
Confirmed land is owned by the City of Tracy
Notice to Proceed to begin Schematic Design
May 2025
Refinements to master budget and schedule
Schematic Design Site Plan and Building Layouts
Technical Meetings with City of Tracy Stakeholders