Emergency Housing

Capital Improvement Project #71112

The low-barrier temporary emergency housing facility project is located on 4.8 acres at 370 W. Arbor Avenue in Tracy California. The project will contain a 151-bed capacity at full build-out and provide access to onsite case management services, restroom and shower facilities, as well as laundry and storage access. Case management services are tailored to individual clients and include connecting those experiencing homelessness with behavioral health services, vital document preparation for housing, medical resources, employment assistance, and additional individualized client resources. The shelter has been open and serving clients since November 2022 and has successfully served over 200 individuals, many into other positive housing destinations.

The current active construction project (Phase II: Site Improvements) began in November 2024 and is planned to be complete by the end of 2025. Multiple contractors have been working at an active shelter environment, and all have been respectful of ongoing shelter operations. During this time, the City of Tracy has continued to coordinate with the active construction projects and concurrent shelter operations. Permanent electrical power and lift station projects began prior to the main construction project with separate individual contractors but are considered part of the Site Improvements phase.

Major Recent Milestone Construction Events

November 2024:

  • Start of Construction
  • Earthwork
  • Site Fencing

December 2024:

  • Over-excavation and site grading
  • Survey staking
  • Landscape and irrigation preparation

January 2025:

  • Continued work at South restroom foundations
  • Excavation of slabs and footings for Sprung Structure foundation
  • Final design for fire sprinkler and fire alarm systems

February 2025:

  • Survey staking at South restroom foundations
  • Sprung structure underground plumbing and electrical work
  • South restroom foundations underground plumbing and electrical work
  • Start of form work at Sprung Structure foundation
  • Start of excavation for bio retention areas as part of stormwater management system
  • Installation of South Location new electrical switchboard

March 2025:

  • Survey staking at South restroom foundations
  • Sprung structure foundation formwork
  • Kitchen underground plumbing and electrical work
  • Start of form work at kitchen foundation
  • Foundation reinforcements

April 2025:

  • Concrete pour at South restroom foundations
  • Continued formwork at kitchen foundation
  • Continued Sprung Structure foundation formwork
  • Installation of Sprung Structure foundation vapor barrier
  • Site perimeter curbs and gutter form work
  • Site perimeter curbs and gutter concrete pours - selected areas
  • Completion of bio retention excavation
  • Pour and placement of site lighting pole bases
  • Sprung Structure Delivery to site
  • Installation of North location new electrical switchboard

May 2025:

  • Sprung Structure foundation pour
  • Continued formwork at kitchen foundation
  • Stormwater management system work
  • Completion of onsite sanitary sewer lift station

Project Completion

The project has been completed as part of four phases.

Groundbreaking ceremony was June 7th, 2022.

Phase 1: Site Preparation (Completed October 2022)

Site Preparation included changes to the existing site to prepare the site to house the temporary emergency housing facility project. Work included demolition of existing onsite structures, significant earthwork and placement of major underground utilities. Site Preparation set the stage for the subsequent Phase II: Site Improvements construction package which incorporates the majority of the overall project's construction.

Phase II: Site Improvements - Congregate Housing and Administrative Offices (Under Construction)

Site Improvements contain much of the project construction and is the last phase to be completed, with an estimated completion date of December 2025. The Site Improvements phase provides a Sprung Structure with a custom interior floor plan layout that allows for three separate congregate dormitories and a day room space. The dormitories can accommodate beds for up to 70 persons. Also included as part of this project phase are restroom and shower facilities and a laundry room facility. These additional facilities will be located adjacent to the Sprung Structure as part of a modular restroom and shower complex. Finally, a modular commercial kitchen facility will allow for onsite preparation of meals to be served at the Sprung Structure's Day room. The Site Improvements phase also includes an asphalt roadway for site vehicular circulation and fire department access, concrete sidewalk surfaces, permeable paver plazas, sight lighting, exterior amenities, cameras, fencing and automatic entry gates. The City is currently working with the design team on final determinations for a modular administration building to be located adjacent to the Sprung Structure and modular commercial kitchen. Other projects completed as part of Site Improvements include smaller separate projects for permanent electrical power and an onsite sanitary sewer lift station.

Phase III: Expansion with Individual Modular Units (Completed November 2022)

The Expansion with Individual Modular Units phase was completed prior to Site Improvements as the need for an operable shelter was required to be met prior to completion of the main construction project. A total of five modular structures were relocated to the site, four of which are dormitories and one of which is an administration structure currently housing shelter operations. These facilities housed the original Temporary Emergency Housing residents and continue to be a fully operational part of the shelter. The Modular Units will remain after completion of Site Improvements and maintain the capacity to house 48 individuals.

Phase IV: Custom Container Dormitories (Completed December 2023)

The Custom Container Dormitories phase built upon the Modular Units to provide additional bed space prior to completion of the main construction project. This phase includes eight custom container dormitory units each housing a maximum of five individual sleeping rooms. In addition, additional restroom and shower spaces are being constructed as part of Site Improvements which will replace current temporary restrooms and showers and will act as permanent restroom and shower facilities to serve these dormitories.

This project is consistent with the City Council's adopted Quality of Life Strategy to continue the implementation of the Homelessness Strategic Plan(PDF, 201KB) and achieve the goal of completing the final site design.

Find more information on the City of Tracy's Homelessness Initiatives.


2022 Project Updates (Archive)

Video Footage of Construction Activity

November 8, 2022 - Interim Shelter Installation

Project Location

370 W. Arbor Avenue, Tracy, CA, 95376

Temporary emergency housing project location map

Timeline

Tentative Project Schedule

  • Advertise for Construction: Fall, 2023
  • Tracy Homelessness Advisory Committee Review of Award
  • Recommendation: Winter, 2023
  • Construction Contract Award: Winter, 2023/24
  • Construction: 300 Business Days in 2024
  • National Environmental Protection Act (NEPA): San Joaquin County conducted an Environmental Assessment in 2023 and released a Finding of No Significant Impact on January 18, 2024

Timeline of Interim Emergency Housing Solutions

Timeline of Interim Emergency Housing Solutions

September 1, 2020

Council direction to move forward with the development of plans for the design and construction of a temporary emergency housing facility.

March 2, 2021

Funding allocated for design and construction

July 13, 2021

June 7, 2022

October 2022

Site Preparation included changes to the existing site to prepare the site to house the temporary emergency housing facility project. Work included demolition of existing onsite structures, significant earthwork and placement of major underground utilities.

November 1, 2022

The Expansion with Individual Modular Units phase was completed prior to Site Improvements as the need for an operable shelter was required to be met prior to completion of the main construction project. A total of five modular structures were relocated to the site, four of which are dormitories and one of which is an administration structure currently housing shelter operations.

December 2023

The Custom Container Dormitories phase built upon the Modular Units to provide additional bed space prior to completion of the main construction project. This phase includes eight custom container dormitory units each housing a maximum of five individual sleeping rooms. In addition, additional restroom and shower spaces are being constructed as part of Site Improvements which will replace current temporary restrooms and showers and will act as permanent restroom and shower facilities to serve these dormitories.

November 2024

  • Start of Construction
  • Earthwork
  • Site Fencing

Site Improvements contain much of the project construction and is the last phase to be completed, with an estimated completion date of December 2025.

Project Renderings / Maps

Temporary Emergency Housing Project Site Rendering

Project plan for City of Tracy Temporary Emergency Housing

Concept Image for Sprung Structure Building

Concept Image of Green tent-like building with windows, doors, and outdoor seating on paved area.

Phase III Site Overview

Aerial view of Phase III Site with buildings, and parking areas

Budget

Capital Expenditures

Secured Project Funding (Capital Funding)

Temporary Emergency Housing Facility CIP 71112

Grants Awarded for Construction:

  • $3,000,000 Community Project Funding Earmarked by Congressman Harder's Office (Pending Environmental Review)
  • $7,167,798 American Rescue Plan Act from San Joaquin County (Pending MOU)
  • $595,000 Health Plan of San Joaquin (pending Council acceptance in Fall 2023)
  • $350,000 Community Development Block Grant from the City of Tracy on September 5, 2023
  • $3,661,113 American Rescue Plan Act from San Joaquin County in July 2021

Grants Awarded for Operations:

  • $251,753 Homeless Housing, Assistance and Prevention (HHAP) for Shelter Operations Accepted by Council on September 5, 2023

Contractor / Consultant

  • Construction Management Services - Roebbelen Construction Management Services, Inc.
  • The KPA Group
  • Shelter Operations (Effective November 1, 2023) - The Salvation Army
  • Shelter Operations (November 1, 2022 - October 31, 2023) - City Net

Contact

Virginia Carney
Homeless Services Manager
HSD@cityoftracy.org
(209) 831-6123

Construction contact information will be posted once awarded.