Seal Coat Program Begins May 18

Published on June 25, 2026

Men holding equipment on street doing seal coating

The City of Tracy will begin its annual Spring–Summer Seal Coat Program on May 18, 2026, marking the start of an eight‑phase effort to preserve and extend the life of neighborhood streets throughout the community. The project is part of the City’s FY 2025–2026 Pavement Preservation Program and includes scheduled work through the beginning of October 2026.

Seal coating is a critical maintenance practice that helps protect roadways from weather damage, prevents small cracks from worsening, and prolongs pavement life—delaying the need for full asphalt replacement, which is significantly more costly and disruptive.

Road Closures and Resident Instructions
Work is weather permitting. On scheduled days, streets will be closed approximately 7:00 a.m. to 5:00 p.m. Residents are asked to remove all vehicles, garbage bins, and basketball hoops from the street before work begins. Vehicles will not be allowed on treated roads during working hours, including cars parked in driveways that require street access.

The City asks all residents to follow the same safety and access procedures used in past seal coat years. Questions may be directed to the Public Works Department.

FY 25–26 Seal Coat Schedule (Summer–Fall)

Beginning May 18, 2026

Below is a summary of the scheduled work based on the City’s final project maps:

  • July 14 – Tanya Ln, Dalehurst Ct, Dalehurst from Dalehurst Ct to Tanya Ln

  • July 15 – Whirlaway Ln (Whispering Wind to Riverview Ave), Riverview Ave (Whirlaway Ln to Calamity Ln), Riverview Ct

  • July 16 – Tamarisk Ln, Dalehurst from Tamarisk Ln to Dalehurst Ct

  • July 21 – Peony Dr from Middlefield Dr to Windsong Dr

  • July 22 – Peony from Chatea Ln to Middlefield Dr, Middlefield Dr from Peony to dead end

  • July 23 – Middlefield Dr from Whispering Wind to Peony Dr

  • July 28 – Chateau Ln, Tropaz Ln from Peony Dr to Chateau Ln

  • July 29 – Bastille Ct, Maison Ct, Peony Dr from Chateau Ln to Maison Ct

  • July 30 – Notre Dame Ct, Memoir Ct, Peony Dr from Maison Ct to Memoir Ct

  • August 4 – Tom Fowler Ct, Darby Ct, Sudeley Dr

  • August 5 – Darby Dr

  • August 6 – Tom Fowler Dr from Sudeley Dr to Windham Dr

  • August 11 – Windham Ct, Windham Dr, Abbyford Ct, Tom Fowler Dr from Windham Dr to Newbury Ct

  • August 12 – Newbury Ln, Whittingham Dr, Farnham Dr, Farnham Ct

  • August 13 – Newbury Ct, Moonlight Wy, Tom Fowler Dr from Newbury Ln to Farnham Dr

  • August 18 – Jonathan Pl, Patch Ln from Jonathan Pl to Sunrise Ct

  • August 19 – Sunrise Ct,Summerset Dr, Patch Ln from Sunrise to Ray Harvey Dr, Ray Harvey Dr from Patch Ln to Summerset Dr

  • August 20 – Pumpkin Ct, Honeydew Ct, Ray Harvey Dr from Summerset Dr to Sycamore Pkwy

  • August 25 – Hoboken Dr, Garden Ln, Garden Ct, Bluegrass Ln from Savanna Dr to dead end

  • August 26 – Meadow Ln, Misty Meadow Dr from Meadow Ln to Blugrass Ln, Bluegrass Ln from Misty Meadow to Savana Dr

  • August 27 – Savanna Dr, Willow Glen Ct, Cornucopia Pl from Savanna Dr to dead end

  • September 1 – Misty Meadow Dr, Cornucopia Pl from Misty Meadow Dr to dead end

  • September 2 – Raindrop Ct, Alfalfa Ct, Cornucopia Pl from Savanna Dr to Misty Meadow Dr

  • September 3 – Peony Dr from Corral Hollow to Memoir Ave

  • September 8 – Calamity Ln, Encanto Ln, Riverview Ave from Encanto to Calamity, Whirlaway Ln from Encanto to middle of the park

  • September 9 – Burr Ct, Troaz Ln from Roxbury to Famoso, Roxbury Dr from Middlefield to Calaveras

  • September 10 – Tropaz Ln from Famoso to Peony

  • September 15 – Famoso Ln, Famoso Ct, Maison Ln from Tropaz Ln to Famoso Ln

  • September 16 – Dally Ct, Roxbury Dr from Calaveras Ln to Maison Ln, Maison Ln from Tropaz Ln to Peony Dr

  • September 17 – Calaveras Ln, Calaveras Ct, Memoir Ave from Calaveras Ln to Remembrance Ln

  • September 21 – Lotus Wy, Lilac Wy, Coloma Ln

  • September 23 –Ponderosa Dr

  • September 24 – Woodbine Wy, Mia Wy

  • September 28 – Aurora Astorga Dr

  • September 30 – Remy Cantos Dr, Carnation Dr

  • October 1 – Starflower from Kagehiro to Buttercup, Buttercup Ln from Mits Wy to Azalea Ave, Azalea Ave from Carnation to Buttercup Ln

  • October 5 – Ivy Ln, Azalea Ave from Ivy Ln to Carnation Dr

  • October 7 – Marigold Dr, Flora Wy, Mits Wy from Ivy Ln to Flora Wy

  • October 8 – Lombard Wy, Sunflower Ln, Buttercup Ln from Sunflower to Mits Wy, Mits Wy from Flora Wy to Buttercup Ln

Why Seal Coat Instead of Repaving?

Seal coating is a preventative maintenance treatment designed to protect roads before they deteriorate.
Seal coat is used when:

  • The pavement is still in good structural condition

  • Early cracks or surface wear are present

  • The goal is to extend pavement life at a low cost

Repaving (overlaying) is used when:

  • The pavement has significant cracking or deformation

  • There are structural failures

  • Large-scale repairs are required

Seal coating costs a fraction of full paving and can extend pavement life by up to 7 years, helping the City reinvest savings into other roadway needs.

 